MISCELLANEOUS SERVICES 

INSTALLATION OF CAPTIVE GENERATING SETS :-(See clause.90-A of Terms and Condition of Supply of Electricity)

Permission of the department shall be obtained before connecting any captive generating set in any premises supplied with electricity by the department. Permission of the Electrical Inspector to Government should also be obtained. This is to ensure that these generating sets do not inadvertently feed into the electric supply system and cause damage to department's property or injury to department's personnel. Violation of this rule will entail immediate disconnection of supply of electricity to the premises and recovery of the cost of damages.

SCHEDULE OF OTHER SERVICES AND CHARGES :- (See clause.105 of Terms and Condition of Supply of Electricity)

The following shall be the various service charges, namely .-

(1) LABOUR AND SUPERVISION CHARGES -

(a) LT Overhead service lines :

(i) One hut one Bulb - Nil
(ii) Other single phase installations - Rs.50/= Per installation.
(iii) Three phase installations - Rs.100/= Per installation.

(b) LT Underground Services lines:

(i) Single Phase installations - Rs.100/= Per installation.
(ii) Three phase installations - Rs.150/= Per installation.

Note: In respect of both (a) and (b) if there are more than one installation to be serviced on the same service line the labour and supervision charges for the second and subsequent installations shall be 50% of the charges as indicated above under item No. (a) (ii) and (iii).

(2) TESTING OF INSTALLATION .-

Testing for servicing a new installation (or of an extension or alteration) - For the first test No Charge

Subsequent testing warranted due to absence of contractor or his representative or due to defects in wiring of consumer's premises:

(i) Domestic lighting/Commercial lighting/IP Installations - Rs. 25.00
(ii) Other LT Installations - Rs. 50.00
(iii) HT/EHT installations - Rs. 200.00

(c) Charges for temporary disconnection at consumer's request - Rs. 25.00

(3) TESTING OF METERS .-

For testing of meter at the instance of the consumer:

(a) Single phase meter - Rs. 25.00
(b) Three phase meter upto 50 Amp - Rs. 50.00
(c) Three phase meter above 50 Amp - Rs. 75.00
(d) HT/EHT installations - Rs. 250.00
(e) Time switches - Rs. 50.00

(4) RATING/RE-RATING OF INSTALLATION .-

For rating/re-rating of installation at the instance of the consumer:

(a) All LT installations - Rs. 100.00
(b) All HT installations - Rs. 250.00

(5) RE-CONNECTION CHARGES .-

(underground or overhead service lines)

(a) Domestic lighting/IP installation - Rs. 5.00
(b) Commercial lighting installation - Rs. 10.00
(c) Any other LT installation - Rs. 25.00
(d) Hut services - Rs. 1.00
(e) HT/EHT installation - Rs. 250.00

(6) TRANSFER OF INSTALLATION

(a) Domestic lighting/IP installation -Rs. 10.00
(b) Commercial lighting installation - Rs. 20.00
(c) All other LT installation - Rs. 50.00
(d) HT/EHT installations - Rs. 250.00

(7) FURNISHING OF CERTIFIED COPIES OF

(To be issued to the consumer only)

(a) Contractor's completion-cum-test report - Rs. 10.00
(b) Ledger extract - Rs. 10.00 per calender year or part thereof.
(c) Agreement - Rs. 10.00
(d) Details of security deposits held - Rs. 10.00
(e) Estimate - Rs. 50.00
(f) Any other document relating to HT/EHT installations - Rs. 10.00 Per sheet.

(8) METER HIRING CHARGES .-

(a) For meters fixed to all service connections under Low Tension supply - NIL
(b) For meters fixed to HT/EHT service connections -
                HT Trivector meter Rs. 250.00 per month.
                LT Trivector meter Rs. 100.00 per month.

(9) SERVICE CALLS .-

(a) Low Tension installation -NIL
(b) High Tension/Extra High Tension installation - Rs 50.00

SHIFTING OF METER BOARD/METERING CUBICLE AT CONSUMER'S REQUEST

(a) LT single phase supply - Rs. 25.00
(b) LT Three phase supply - Rs. 50.00
(c) HT supply - Rs. 250.00

Note: The actual work shall be got carried out by the consumer at his cost through the contractor after obtaining necessary line clear from the department.

(10-A) Tranformer Oil Testing Charges:Di-electric Strength Test (for a set of sample at a time)- Rs. 280/-

(10-B) Testing Charges for Protection Switchgear equipment in HT/EHT installations:-

1. Testing Charge for one set of relays (3-phase line fault or one earth leakage with 2-phase line fault condition)- Rs. 2,500.00
2. Testing charge for one set of Current Transformer - Rs. 2,500.00
3. Testing charge for one set of Potential Transformer - Rs. 2,500.00
4. Testing of one set of Circuit Breaker - Rs. 2,500.00
5. Charge for measurement of earth resistance - Rs. 1,000.00

MISCELLANEOUS WORKS:-

The charges payable in advance for any work which the department may undertake for the consumer and which is not included in the above schedule shall be, cost of materials and labour plus 18% to cover overhead charges. Estimates will be furnished when necessary.