REDUCTION OF LOAD

Reduction In Contract Demand / Sanctioned Load :-

During the agreement period initial or extended, the consumer is entitled to get his contract demand/sanctioned load reduced by executing a fresh agreement. The reduction will be given effect to from the meter reading date following the expiry of 3 months period from the date of receipt of his request by the department. However, the minimum charge payable by the consumer in respect of the previous agreement shall be guaranteed against the current consumption charges payable against the new agreement by the consumer.