| (a) |
Low Tension Service connections |
|
|
| i) |
If the total load in addition to the proposed
load is within 90% of the capacity of existing transformer and the scheme proves to be
self-remunerative. |
- |
Power Feasibility Certificate will be issued
within 10 days after receipt of the application. |
| ii) |
If the total load in addition to the proposed
load is more than 90% of the capacity of existing transformer and the scheme proves to be
self-remunerative. |
- |
Will be isssued within 30 days after receipt of
the application. |
| (b) |
High Tension Service connections |
|
|
| i) |
If the contracted maximum demand is less than 500
KVA. |
- |
Within 30 days after submitting all the necessary
documents. |
| ii) |
If the contracted maximum demand is including or
more than 500 KVA. |
- |
After submitting all the necessary documents and
within 20 days after obtaining the Government sanction. |