II. ISSUE OF POWER FEASIBILITY CERTIFICATE


(a) Low Tension Service connections
i) If the total load in addition to the proposed load is within 90% of the capacity of existing transformer and the scheme proves to be self-remunerative. - Power Feasibility Certificate will be issued within 10 days after receipt of the application.
ii) If the total load in addition to the proposed load is more than 90% of the capacity of existing transformer and the scheme proves to be self-remunerative. - Will be isssued within 30 days after receipt of the application.
(b) High Tension Service connections
i) If the contracted maximum demand is less than 500 KVA. - Within 30 days after submitting all the necessary documents.
ii) If the contracted maximum demand is including or more than 500 KVA. - After submitting all the necessary documents and within 20 days after obtaining the Government sanction.