| i) |
Acknowledgement of receipt of service
connection application along with required documents. |
- |
Within 3 days |
| ii) |
Scrutiny of application, informing
about the discrepancies in the application. |
- |
Within 7 days after receipt of application |
| A) |
Schemes costing less than Rs. 2,00,000: |
| a) |
Preparation of estimate and sanction
for extension of power supply. |
- |
Within 30 days from the date of receipt of
application in section office. |
| b) |
Collection of Security Deposit and
executive of agreement |
- |
Within 7 days from the date of sanction if
applicant is ready. |
| c) |
Execution of HT line extension,
Double Pole structure works subject to availability of materials, priority and site
condition. |
- |
Within 30 days after payment of Security Deposit. |
| d) |
Provision of metering arrangements |
- |
10 days after completion of work |
| e) |
Effecting service connection after
payment, after fixing the meter at the consumer premises . |
- |
Within 10 days after completion report with all
the required clearances by the applicant. |
| B) |
Schemes costing more than Rs. 2,00,000 but less than Rs 5,00,000: |
| a) |
Preparation of estimate for extension
of power supply. |
- |
Within 30 days from the date of receipt of
application in section office. |
| b) |
Collection of Security Deposit and
execution of agreement. |
- |
Within 7 days from the date of sanction if
applicant is ready. |
| c) |
Execution of HT line extension,
Double Pole structure works subject to availability of materials, priority and site
condition. |
- |
Within 60 days after payment of Security Deposit. |
| d) |
Provision of metering arrangements |
- |
10 days after completion of work |
| e) |
Effecting service connection after
payment, after fixing the meter at the consumer premises. |
- |
Within 10 days after completion report with all
the required clearances by the applicant. |
C) |
Schemes costing more than Rs. 5,00,000 |
| a) |
Preparation of estimate and sanction
for extension of power supply. |
- |
Within 30 days from the date of receipt of
application in section office. |
| b) |
Collection of Security Deposit and
execution of agreement |
- |
Within 7 days from the date of sanction if
applicant is ready. |
| c) |
(i) |
Execution of HT line extension, Double Pole
structure works subject to availability of materials, priority and site condition (without
erection of new feeder). |
- |
Within 90 days after payment of Security Deposit |
|
(ii) |
Execution of line work involving provision of new
/ additional feeder arrangement from the Sub-Station. |
- |
Within 180 days after payment of Security Deposit |
| d) |
Provision of metering arrangements |
- |
10 days after completion of work |
| e) |
Effecting service connection after
payment, after fixing the meter at the consumer premises. |
- |
Within 10 days after completion report with all
the required clearances by the applicant. |