Permanent Service Connection

II. Low Tension Service Connection (Domestic and Commercial Services Above 10 KW)


i) Acknowledgement of receipt of application with required documents. - Within 1 day
ii) Scrutiny of application, informing about the discrepancies in the application. - Within 5 days after receipt of application
A) Schemes costing less than Rs.2,00,000:
a) Preparation and sanction of estimate for extension of power supply to the service connection. - Within 45 days from the date of receipt of application in section office.
b) Execution of line works subject to availability of material and priority and site condition. - 45 after receipt of sanction
c) Effecting Service Connection - Within 10 days after payment of security deposit, service connection charges etc.
B) Schemes costing more than Rs 2,00,000:
a) Preparation and sanction of estimate for extension of power supply to the service connection. - Within 60 days from the date of receipt of application in section office.
b) Execution of line works subject to availability of material and priority and site condition. - 75 days after receipt of sanction
c) Effecting service connection - Within 10 days after payment of security deposit, service connection charges etc.