| i) |
Acknowledgement of receipt of application with
required documents. |
- |
Within 1 day |
| ii) |
Scrutiny of application, informing about the
discrepancies in the application. |
- |
Within 5 days after receipt of application |
| A) |
Schemes costing less
than Rs.2,00,000: |
| a) |
Preparation and sanction of estimate for
extension of power supply to the service connection. |
- |
Within 45 days from the date of receipt of
application in section office. |
| b) |
Execution of line works subject to availability
of material and priority and site condition. |
- |
45 after receipt of sanction |
| c) |
Effecting Service Connection |
- |
Within 10 days after payment of security deposit,
service connection charges etc. |
| B) |
Schemes costing more
than Rs 2,00,000: |
| a) |
Preparation and sanction of estimate for
extension of power supply to the service connection. |
- |
Within 60 days from the date of receipt of
application in section office. |
| b) |
Execution of line works subject to availability
of material and priority and site condition. |
- |
75 days after receipt of sanction |
| c) |
Effecting service connection |
- |
Within 10 days after payment of security deposit,
service connection charges etc. |