| i) |
Acknowledgement of receipt of service
connection application along with required documents. |
- |
Within 1 day |
| ii) |
Scrutiny of application, informing about the
discrepancies in the application. |
- |
Within 5 days after receipt of application |
| iii) |
On Line |
|
|
| a) |
Preparation of estimate for extension of power supply to
the service connection. |
- |
Within 5 days from the date of receipt of application in
section office. |
| b) |
Effecting service connection. |
- |
Within 7 days after payment of security deposit, service
connection charges etc. |
| iv) |
Minor Extension |
|
|
A) |
Where distance is 200 m from the existing
line: |
|
|
| a) |
Preparation and Sanction of estimate for extension of
power supply to the service connection. |
- |
Within 15 days from the date of receipt of application in
section office |
| b) |
Execution of line works subject to availability of
material and priority and site condition. |
- |
Within 15 days from the date of receipt of sanction |
| c) |
Effecting service connection |
- |
Within 7 days after payment of security deposit, service
connection charges etc. |
B) |
Where the distance is more than 200 m: |
|
|
| a) |
Preparation and sanction of estimate for extension of
power supply to the service connection. |
- |
Within 15 days from the date of receipt of application in
section office |
| b) |
Execution of line works subject to availability of
material and priority and site condition. |
- |
20 days after receipt of sanction |
| c) |
Effecting Service Connection |
- |
Within 7 days after payment of security deposit, service
connection charges etc. |
|
CABLE |
|
|
| i) |
Acknowledgement of receipt of service connection
application along with required documents. |
- |
Within 1 day |
| ii) |
Scrutiny of application, informing about the
discrepancies in the application. |
- |
Within 5 days after receipt of application |
| iii) |
On Line |
|
|
| a) |
Preparation of estimate for service connection
application and extension of power supply to the service connection. |
- |
Within 5 days from the date of receipt of application in
seciton office |
| b) |
Effecting service connection |
- |
Within 10 days after payment of security deposit, service
connection charges and obtaining permission from the municipality for road cutting. |