ELECTRICITY DEPARTMENT
SERVICES RENDERED
The Electricity Department provides the following services to
the people of Union Territory of Puducherry. According to their needs, the public can
approach the concerned for availing Services/Particulars in the Electricity Department.
(a) Availing of new service connection to domestic,
Commercial, Industrial and agriculture.
(b) Name transfer and shifting of service connection.
(c) Enhancement of load.
(d) Rectification of defective meter.
(e) Change of tariff.
(f) Revision/conversion of current consumption charge bill.
(g) Issue of Power Feasibility Certificate.
(h) If any defects found in distribution of power is to be rectified.
(i) New street lights to be installed on the basis of Municipalities or
Commune Panchayats resolution.
*(j) Intimation of appropriate action taken on the petitions received from the
public.
**(k) Hearing and readdressal of public grievances and rectification of the complaint.
Apart from the above services, the services (j) and (k)
rendered by this Department are as detailed below:-
* If the public have addressed their grievances/petitions to the Superintending
Engineer-I or Post Box No. 333, Electricity Department, Puducherry the particulars
regarding the action on the petition is available from the Public Relation Officer at the
I floor, Room No. 102 New Building , Electricity Department, Puducherry.
** Apart from the above services, if the public requires any particulars/services, they
can approach the "Information Centre" which is exiting near the entrance at Main
office.
The Electricity Department is divided into three Circles and
functioning under the administrative control of Superintending Engineer-I as Head of
Department. The jurisdictional area and address of the three Superintending Engineers are
given below:-
| (a) |
Superintending Engineer-I
Electricity Department (Main Office)
137, Subbash Chandra Bose Salai
Puducherry- 605 001 |
Overall Administration (whole Union Territory of Puducherry) |
| (b) |
Superintending Engineer-II
Electricity Department (Main Office)
137, Subbash Chandra Bose Salai
Puducherry- 605 001 |
Operation and maintenance of Karaikal, Mahe and Yanam region. |
| (c) |
Superintending Engineer-III
Electricity Department (Main Office)
137, Subbash Chandra Bose Salai
Puducherry- 605 001 |
Operation and Maintenance of Puducherry region. |
The Public of Puducherry region who encounter any
delay in redressal of their grievances may approach the Superintending Engineer-III
at the above mentioned address for Salvation. The public living in Karaikal, Mahe
and Yanam regions may approach the Superintending Engineer-II at the above
mentioned address for salvation of their long pending problems. For the entire U.T. of
Puducherry, the public may approach the Superintending Engineer-I.
EXECUTIVE ENGINEER-I (TOWN)
137, Subbash Chandra Bose Salai
ELECTRICITY DEPARTMENT
NEW BUILDING, II FLOOR
Puducherry
Phone : Office : (0413) 233 9543
The following Subdivision Offices and the respective jurisdictional areas
under the control of Division-I are detailed below. The public residing in the below
mentioned area can approach their concerned Officers for availing of different services
rendered by this Department. Besides the public may also contact the respective Fuse-off
Call Office either in person or over phone for rectification of defects in supply of
Electricity.
Officer |
Areas |
Assistant
Executive Engineer / Town-I
Electricity Department (MainOffice)
137, Subbash Chandra Bose Salai
Puducherry - 605 001.
Phone Office: 233 6361-65 & 222 2270 - 74 Extn: 526
Phone Residence: 220 0960 |
(i) Fuse-off Call Office :
Town South
Phone : 233 6361-65 & 222 2270-74
Extn: 527
From Kandappa Mudali Street to Subbaiah Salai which includes Vanarapet, Kolas Nagar,
Nethaji Nagar, Vambakeerapalayam, Dubrayapet.
(ii) Fuse-off Call Office: Town North
Phone: 233 6327
From Perumal Koil Street to Chinnayapuram, Thiruvalluvar Nagar, Vazhaikulam, Vaithikuppam,
portion of White Town (From Rangapillai Street to S.V.Patel Salai).
(iii) Fuse-off Call Office: Town Central
Phone: 233 6327
From Needarajappaiyar Street to Muthumariamman Koil Street.
(iv) Fuse-off Call Office: Town South-Central
Phone: 233 6299
Vanarapet North, Govindasalai (Upto Needarajappaiyar Street, Ambour Salai, Botanical
Garden). |
Assistant Engineer
/ Town-II
100, Perumal Koil Street
Puducherry
Phone Office: 233 6327
Phone Residence :
|
(i) Fuse-off Call Office:
Muthialpet
Phone: 223 6166
Muthialpet (Northern Border of Puducherry) and portion of Karuvadikuppam.
(ii) Fuse-off Call Office: Saram
Phone: 220 0776
Mohan Nagar, Ellapillaichavady, Saram, Pillaithottam, Kuyavarpalayam, Periyar Nagar,
Saradambal Nagar, portion of Kamaraj Salai.
(iii) Fuse-off Call Office: Venkata Nagar
Phone: 221 0361
Chellan Nagar, Kamarajar Nagar, Nehru Nagar, Chittankudisai, Brindavanam, Elango Nagar,
Santhi Nagar, Rajarajeshwari Nagar, Chellan Nagar, Kamaraj Nagar, Nehru Nagar,
Chithankudisai, Brindavanam, Elango Nagar, Santhi Nagar, Rajaji Nagar, Kumaragururpallam
and portion of Kamarajar Street. |
Assistant Engineer
/ Marapalam S.S
Sub-Station Campus
Cuddalore Road, Marapalam
Puducherry-605004
Phone :235 8547 |
(i) Fuse-off Call Office:
Mudaliarpet
Phone: 235 7697
From Railway crossing at Cuddalore Road upto Murungapakkam Bridge, Thengaithittu portion
and Uzhavarkrai South.
(ii) Fuse-Off Call Office: Town West
Phone: 220 3110
From Attupatti Anthoniar Koil junction upto Reddiarplayam from Karamanikuppam upto
Ellaipillachavady.
(iii) Fuse -Off Call Office: Murungapakkam
Phone: 235 7362
Velrampet, Nagammal Nagar, Pudhu Nagar, Priyadharsni Nagar, NainarMandabam, Mookambigai
Nagar, Thakka Thoppu, Murungapakkampet Papanchavadi, Ottenpalayam upto Kobakkampet. |
Besides, if there happens to be
any delay in services rendered by this Department, the public may approach the Executive
engineer (Town) at the above mentioned address for redressal of their grievances.
EXECUTIVE ENGINEER-IV (NORTH)
ELECTRICITY DEPARTMENT
HEAD OFFICE CAMPUS
137, SUBBASH CHANDRA BOSE SALAI
Puducherry - 605 001
Telephone Office : (0413) 233 4279 Residence : 225 2286
The following Subdivision Offices and the respective jurisdictional areas
under the control of Division-IV are as detailed below. The public residing in the
below mentioned area can approach their concerned Officers for availing of different
services rendered by this Department. Besides the public may also contact the respective
Fuse-off Call Office either in person or over phone for rectification of defects in supply
of Electricity.
Officer |
Areas |
Assistant Engineer
/ Lawspet
Electricity Department
1, Elango Street
Anandha Nagar
Kathirkamam
Puducherry-9
Phone Office: 227 3768
|
(i) Fuse-off Call Office :
Lawspet
Phone : 225 3124
Karuvadikuppam, Lawspet, Pakkamudayanpet, Rajaji Nagar and Tagore Nagar.
(ii) Fuse-off Call Office: Ashok Nagar
Phone: 225 7100
Tagore Arts College Complex, Kurunji Nagar, Kumaran Nagar, Ashok Nagar, Chozan Nagar anf
Government Servants Quarters.
(iii) Fuse-off Call Office: Gorimedu
Phone: 224 8093
From Chain Factory up to Gorimedu (Puducherry Border), from Subbaiah Nagar to Kadirkamam
and Thattanchavady.
|
Assistant Engineer /
Kalapet
Sub-Station Campus
Kalapet, Puducherry
Phone Office: 265 5180 |
(i) Fuse-off Call Office :
Kalapet
Phone : 265 5181
Kalapet, Chinnakalapet, Kanagachettikulam, Alankuppam including nearby villages. |
Assistant Engineer
/ Kurumbapet
Sub-Station Camplex
PIPDIC Industrial Estate,
Kurumbapet, Puducherry
Phone Office: 227 5711 |
(i) Fuse-off Call Office :
Muthirapalayam
Phone : 227 5744
Shanmugapuram, Muthirapalayam, Mettupalayam, PIPDIC Industrial Estate, Thakkakuttai,
Oulgaret, Moolakulam and Pitchaveeranpet. |
Assistant Engineer
/ Boomiyanpet
Boomiyanpet Housing Board Campus
Boomiyanpet
Puducherry
Phone Office: 220 0200
Phone Residence: 227 4218
|
(i) Fuse-off Call Office:
Boomiyanpet
Phone: 220 5205
Vivekanantha Nagar, Victoria Nagar, Boomiyanpet Housing Board Campus, Agiz
Nagar,Pavazhakaranchavady, Kamban Nagar, Jaya Nagar, Pudhu Nagar, Marial Nagar, Kaveri
Nagar,portion of Oulgarpet, South Oulgaret, Moolakulam and portion of Pitchaveeranpet.
(ii) Fuse-off Call Office : Villianur
Phone : 266 6324
Arumparthapuram, Villianur, Odiampet and Kompakkam. |
Assistant Engineer
/ Sedharapet
Electricity Department
Sub Station Campus
PIPDIC Industrial Estate
Sedharapet
Puducherry
Phone Office: 267 7390
|
(i) Fuse-off Call Office:
Seduarpet
Phone: 267 7906
Sedharapet, Karasur, Sedharapet Industrial Estate.
(ii) Fuse-off Call Office : Ramanathapuram
Phone : 266 6374
Pathukannu, Ramanathapuram, Pillaiyarkuppam, Thuthipet, Thondamanathan, Koodapakkam. |
Assistant Engineer
/ Thethampakkam
Electricity Department
Sub Station Campus
Thethampakkam
Puducherry
Phone Office: 267 4975
|
(i) Fuse-off Call Office:
Katterikuppam
Phone: 267 7898
Katterikuppam, Lingareddipalayam, Kumarapalayam, Suthukeni, Thethampakkam, Pudhukuppam,
Sandaipudhukuppam, and Kuppam.
(ii) Fuse-off Call Office : Thirukkanur
Phone : 268 8471
Mannadipet, Koonichampet, Thirukanur, Sorapet and Sellipet.
(iii) Fuse-off Call Office : Vadhanur
Phone : 268 0044
Vadhanur, Sorapet, Mannadipet, Vinayagampet, Sellipet, Vambupet, Puranasingapalayam. |
Besides, if there happens to be any delay in services
rendered by this Department, the public may approach the Executive engineer (North) at the
above mentioned address for redressal of their grievances.
EXECUTIVE ENGINEER-IX (SOUTH)
MARAPALAM SUBSTATION CAMPUS
CUDDALORE ROAD, MARAPALAM
Puducherry-605 004
Telephone Office : 235 8564 Residence :
The following Subdivision Offices and the respective jurisdictional areas
under the control of Division are as detailed below. The public residing in the
below mentioned area can approach their concerned Officers for availing types of
services rendered by this Department. Besides the public may also contact the
respective Fuse-off Call Office either in person or over phone for rectification of
defects in supply of Electricity.
Officer |
Areas |
Assistant
Engineeer / Thirubuvanai
Thirubuvanai Sub - Station Campus
Villupruam Road
Puducherry
Phone Office: 264 1144
|
(i) Fuse-off Call Office :
Thiruvandar Koil
Phone : 264 0149
Thiruvandar Koil, Madagadipet, Puranasingapalayam and Nallur. |
Assistant Engineer
/ Eripakkam
Eripakkam Sub - Station Campus
Puducherry
Phone Office: 269 9494
|
(i) Fuse-off Call Office :
Kariamanickam
Phone : 269 9448
Eripakkam, Madukarai and Kalmandapam.
(ii) Fuse-off Call Office : Karayamputhur
Phone : 269 8856
Kaduvanur, Manalmedu and Karayamputhur. |
Assistant Engineer
/ Rural South
Marapalam Sub - Station Campus
Marapalam
Cuddalore Road
Puducherry - 605 004
Phone Office: 235 8564
|
(i) Fuse-off Call Office :
Ariyankuppam
Phone : 260 0340
Ariyankuppam, Manaveli, Radhakrishna Nagar, Veerampattinam and Chinnaveerampattinam.
(ii) Fuse-off Call Office : Karikalampakkam
Phone : 266 6369
Karikalampakkam, Korkadu, Peranglore and Santhamangalam.
(iii) Fuse-off Call Office : Vadamangalam
Phone : 266 6606
Vadamangalam, Ariyur, Sivarandhagam, Uruvaiyar, Thirukanjee and Mangalam. |
Assistant Engineer
/ Bahour
Bahour Sub - Station Campus
Cuddalore Road, Kattukuppam
Puducherry
Phone Office: 261 1577
|
(i) Fuse-off Call Office :
Bahour
Phone : 263 3444
Kanniakoil, Nirnayampet, Irulanchandai and Suruliankuppam.
(ii) Fuse-off Call Office : Kirumampakkam
Phone : 261 1129
Kirumampakkam, Mullodai, Pillaiyarkuppam and Pinachikuppam
(iii) Fuse-off Call Office : Thavalakuppam
Phone : 2618202
Thavalakuppam, Thennampalayam, Nallavadu, Korkamedu, Abizhegapakkam, T.N.Palayam and
Andiyarpalayam. |
Besides, if there happens to be any delay in services
rendered by this Department, the public may approach the Executive Engineer (South) at the
above mentioned address for redressal of their grievances.
SUPERINTENDING ENGINEER-I
EXECUTIVE ENGINEER-V (KARAIKAL)
7, KIRAMBUTHOTTAM SOUTH STREET
KARAIKAL
Telephone Office : 04368- 222 694 , Residence : 04398-222 684
The following Subdivision Offices and the respective jurisdictional areas
under the control of Division are as detailed below. The public residing in the below
mentioned area can approach their concerned Officers for availing types of services
rendered by this Department. Besides the public may also contact the respective Fuse-off
Call Office either in person or over phone for rectification of defects in supply of
Electricity.
Officer |
Areas |
Assistant Engineer
/ Town
7, Kirambuthottam South Street
Karaikal
Phone Office: 04368 - 222 598
Phone Residence: 04368 - 226 599 |
(i) Fuse-off Call Office :
Town
Phone : 04368 - 222 428
Whole Karaikal Town, Pudhuthurai, Darumapuram, Pachur and Thakkalur.
(ii) Fuse-off Call Office : Town North
Phone: 04368 - 230 798
Kovilpathu, Nehru Nagar, Thalatheru, Karaikalmedu, Kilinjalmedu, Ammankovilpathu,
Pillaitheruvasal, Ammayar Nagar, Keezhakasakudi, Kottuchery, Kottucherimedu,
Keezhakasakudimedu, Rayanpalayam, Koozkuditha, Pulianthippu, Varichikudi, Thiruvettakudi,
Kalikuppam, Akkampet, Mandapathur, Kuppuchetty and Poovam.
(iii) Fuse-off Call Office : Thirumalairayanpattinam
Phone: 04368 - 234 492
Thirumalairayanpattinam, Polagam, Keezhavanjur, Melavanjur, Vadakkuvanjur, Mudalimedu and
Pattinacherry.
(iv) Fuse-off Call Office : Neravy
Phone:04368 - 238 798
Vadakattalai, Nainikattalai, Padudarkollai, Melaiyurpettai, Idatheru, Neravy, Oozhipathu,
Thootupona-moolai, Kakamozhi, Keezhamanai, Manjavazhipattu, Melaoduthurai,
Keezhaodutharai, Naduoduthurai, Karukalacherry and Akkaraivattam. |
Assistant Engineer
/ Rural
7, Kirambuthottam South Street
Karaikal
Phone Office: 04368 - 222 598
|
(i) Fuse-off Call Office :
Thirunallar
Phone : 04368 - 236 674
Thirunallar, Athipadukai, Pettai, Sellur, Thennangudi, Agalankannu, Ilaingankudi,
Surakudi, Karukkankudi, Thenur, Vizhithiyur and Manampettai.
(ii) Fuse-off Call Office : Ambagarathur
Phone: 04368 - 252 397
Ambagarathur, Thamanangudi, Kannapur, Nallazhundur, Nallambal, Kumarakudi, Chethur,
Thenpidagai, Valathamangalam, Pandaaravadai, Vadaku Kottapady, Maadur and Moppayithangudi.
(iii) Fuse-off Call Office : Nedungadu
Phone: 04368 - 261 228
Nedungadu, Panchatcharam, Annavasal, Parutikudy, Agaramangudi, Kurumbagaram,
Pandaaravaadai, Mathalankudi, Narikurumbai,Nallathur, Adaikalanpuram, Kottanpakkam,
Saravanairuppu, Vadakattalai, Kulakudi, Anjur, Usuppar, Kottagam,
Kilianur,Melakottucherry, Melakasakudi, Chembiankal, Thiruvenkatapuram,Devemauram,
Chembiankal, Thiruvenkatapuram, Devemapuram,Pathakudi, Serumavilangai, Suppurayapuram and
Keezhavur.
|
Besides, if there happens to be any delay in services
rendered by this Department, the public may approach the Executive Engineer (Karaikal) at
the above mentioned address for redressal of their grievances.
SUPERINTENDING ENGINEER-I
MAHE REGION
The Electricity Department provides the following services to the people of
Mahe. According to their needs the public can approach the concerned Officer for availing
the Services/Particulars in the Electricity Department.
(a) Availing of new service connection to domestic, commercial, industrial
and Agriculture.
(b) Name transfer and shifting of service connection.
(c) Enhancement of load.
(d) Rectification of defective meter.
(e) Change of tariff.
(f) Revision/correction of current consumption bill.
(g) Issue of Power Feasibility Certificate.
(h) Intimation of appropriate actions on the petitions received from the public.
(i) Hearing and redressal of public grievances and rectification of the complaint.
The Superintending Engineer-II is the overall incharge of the Mahe region
and the Executive Engineer-III is looking after the Operation and Maintenance of the Mahe
region, whose addresses are given below:
THE SUPERINTENDING ENGINEER-II
ELECTRICITY DEPARTMENT (MAIN OFFICE)
137, SUBBASH CHANDRA BOSE SALAI
Puducherry 605 001
Telephone Office :0413 - 234 3687 |
THE EXECUTIVE ENGINEER-III
ELECTRICITY DEPARTMENT (MAIN OFFICE)
137, SUBBASH CHANDRA BOSE SALAI
Puducherry 605 001
Tele. Off : 0413 - 233 8689 |
The Subdivision Officer and the respective
jurisdictional areas under the control of the Sub divisional Officer are as detailed
below. The public residing at the below mentioned area may approach their concerned
officers for availing the Services / Particulars in the Electricity Department. Besides,
the public may also contact the respective Fuse-off Call Office either in person or over
phone for rectification of defects in supply of Electricity.
Officer |
Areas |
Assistant Engineer
/ Mahe
Electricity Department
Main Road
Mahe
Phone Office: 0490 - 233 5666
|
(i) Fuse-off Call Office :
Mahe
Phone : 0490 - 233 2224
Whole Mahe Town and Chembra Village.
(ii) Fuse-off Call Office: Palloor
Phone: 0490 - 233 2624
Palloor, Pandakkal, East Palloor, Chalakkara, Cherukallayui. |
Besides, if there happens to be any delay in services
rendered by this Department the public may approach the Executive Engineer-III at the
above mentioned address for redressal of their grievances.
YANAM REGION
The Electricity Department provides the following services to the people of
Yanam region. According to their needs the public can approach the concerned Officer for
availing the Services / Particulars in the Electricity Department.
|
(a) Availing of new service connection to domestic, commercial,
industrial and Agriculture.
(b) Name transfer and shifting of service connection.
(c) Enhancement of load.
(d) Rectification of defective meter.
(e) Change of tariff.
(f) Revision/correction of current consumption bill.
(g) Issue of Power Feasibility Certificate.
(h) Intimation of appropriate actions on the petitions received from the public.
(i) Hearing and redressal of public grievances and rectification of the complaint. |
The Superintending Engineer-II is the overall incharge of the Yanam region
and the Executive Engineer-VII is looking after the Operation and Maintenance of the Yanam
region, whose addresses are given below:
THE SUPERINTENDING ENGINEER - II
ELECTRICITY DEPARTMENT (MAIN OFFICE)
137, SUBBASH CHANDRA BOSE SALAI
Puducherry 605 001
Telephone Office : 0413 - 234 3687 |
THE EXECUTIVE ENGINEER - II
ELECTRICITY DEPARTMENT (MAIN OFFICE)
137, SUBBASH CHANDRA BOSE SALAI
Puducherry 605 001
Tele Off : 0413- 222 5552 |
The Subdivision Officer and the respective jurisdictional areas under the
control of the Sub divisional Officer, Yanam are as detailed below. The public residing at
the below mentioned area can approach their concerned Officers for availing types of
services rendered by this Department. Besides, the public may also contact the respective
Fuse-off Call Office either in person or over phone for rectification of defects in supply
of Electricity.
Officer |
Areas |
Assistant Engineer
/ Yanam
Electricity Department
No. 4-80, New Bus Stand
Yanam
Phone Office:0884 - 232 1278
|
(i) Fuse-off Call Office :
Yanam
Phone : 0884 - 232 1278
Mettacura, Kanakalapeta, Kurusumpeta, Parampeta, Dommetivaripeta, Issukkalava, Seetharama
Nagar, Darialathippa, Giriampeta, Savithri Nagar and Yanam Town. |
Besides, if there happens to be any delay in services
rendered by this Department, the public may approach the Executive Engineer-X at the above
mentioned address for redressal of their grievances.
SUPERINTENDING ENGINEER-I
I PERMANENT SERVICE CONNECTION
| I. Low
Tension Service Connection (Domestic, Commercial, upto 10 kW)
| i) |
Acknowledgement of receipt of service connection
application along with required documents. |
- |
Within 1 day. |
| ii) |
Scrutiny of application, informing about the
discrepancies in the application. |
- |
Within 5 days after receipt of application. |
| iii) |
ON LINE |
|
|
a) |
Preparation of estimate for extension of power
supply to the service connection. |
- |
Within 5 days from the date of receipt of
application in section office. |
b) |
Effecting service connection. |
- |
Within 7 days after payment of security deposit,
service connection charges etc. |
| iv) |
MINOR EXTENSION |
|
|
A) |
Where distance is 200 m from the existing line: |
a) |
Preparation and Sanction of estimate for
extension of power supply to the service connection. |
- |
Within 15 days from the date of receipt of
application in section office. |
b) |
Execution of line works subject to availability
of material and priority and site condition. |
- |
Within 15 days from the date of receipt of
sanction |
c) |
Effecting service connection |
- |
Within 7 days after payment of security deposit,
service connection charges etc. |
B) |
Where the distance is more than 200 m: |
a) |
Preparation and sanction of estimate for
extension of power supply to the service connection. |
- |
Within 15 days from the date of receipt of
application in section office. |
b) |
Execution of line works subject to availability
of material and priority and site condition. |
- |
20 days after receipt of sanction. |
c) |
Effecting Service Connection |
- |
Within 7 days after payment of security deposit,
service connection charges etc. |
|
CABLE |
|
|
| i) |
Acknowledgement of receipt of service connection application
along with required documents. |
- |
Within 1 day |
| ii) |
Scrutiny of application, informing about the discrepancies in
the application |
- |
Within 5 days after receipt of application. |
| iii) |
ON LINE |
|
|
a) |
Preparation of estimate for service connection
application and extension of power supply to the service connection |
- |
Within 5 days from the date of receipt of
application in section office. |
b) |
Effecting service connection |
- |
Within 10 days after payment of security deposit,
service connection charges and obtaining permission from the municipality for road
cutting. |
II. Domestic and Commercial
Services (Above 10 kW)
| i) |
Acknowledgement of receipt of
service connection application along with required documents. |
- |
Within 1 day |
| ii) |
Scrutiny of application, informing
about the discrepancies in the application. |
- |
Within 5 days after receipt of application. |
| A) |
Schemes costing less than Rs.2,00,000: |
| a) |
Preparation and sanction of
estimate for extension of power supply to the service connection |
- |
Within 45 days from the date of receipt of
application in section office. |
| b) |
Execution of line works subject to
availability of material and priority and site condition |
- |
45 days after receipt of sanction |
| c) |
Effecting service connection |
- |
Within 10 days after payment of security deposit,
service connection charges etc. |
| B) |
Schemes costing more
than Rs.2,00,000: |
| a) |
Preparation and sanction of
estimate for extension of power supply to the service connection. |
- |
Within 60 days from the date of receipt of
application in section office. |
| b) |
Execution of line works subject to
availability of material and priority and site condition. |
- |
75 days after receipt of sanction. |
| c) |
Effecting service connection |
- |
Within 10 days after payment of security deposit,
service connection charges etc. |
III. Low Tension Industries
upto 5 H.P.
| i) |
Acknowledgement of receipt of
service connection application along with required documents. |
- |
Within 1 day |
|
|
|
|
| ii) |
Scrutiny of application, informing about the discrepancies in
the application. |
- |
Within 7 days after receipt of application. |
|
|
|
|
| iii) |
Preparation and sanction of estimate for extension of power
supply to the service connection. |
- |
Within 10 days from the date of receipt of application in
section office. |
|
|
|
|
| iv) |
Effecting service connection |
- |
Within 7 days after payment of security deposit, service
connection charges etc. |
IV. Low Tension Industries above 5
H.P
| a) |
Acknowledgement of receipt of service connection application
along with required documents. |
- |
Within 1 day |
|
|
|
|
| b) |
Scrutiny of application, informing about the discrepancies in
the application. |
- |
Within 7 days after receipt of application. |
|
|
|
|
| A) |
Schemes costing less than Rs.2,00,000: |
|
|
| a) |
Preparation and sanction of estimate for extension of power
supply to the service connection |
- |
Within 45 days from the date of receipt of application in
section office. |
|
|
|
|
| b) |
Execution of line works subject to availability of material
and priority and site condition. |
- |
45 days after receipt of sanction. |
|
|
|
|
| c) |
Effecting service connection after payment, after fixing the
meter at the consumer premises. |
- |
Within 10 days after payment of security deposit. |
|
|
|
|
| B) |
Schemes costing more than Rs.2,00,000: |
|
|
| a) |
Preparation and sanction of estimate for extension of power
supply to the service connection. |
- |
Within 60 days from the date of receipt of application in
section office. |
|
|
|
|
| b) |
Execution of line works subject to availability of material
and priority and site condition. |
- |
75 days after receipt of sanction. |
|
|
|
|
| c) |
Effecting service connection after payment, after fixing the
meter at the consumer premises. |
- |
Within 10 days after payment of security deposit. |
V. High Tension Industries
| i) |
Acknowledgement of receipt of service connection
application along with required documents. |
- |
Within 3 days |
|
|
|
|
| ii) |
Scrutiny of application, informing about the
discrepancies in the application. |
- |
Within 7 days after receipt of application. |
|
|
|
|
A) |
Schemes costing less than Rs.2,00,000: |
|
|
| a) |
Preparation of estimate and sanction for
extension of power supply. |
- |
Within 30 days from the date of receipt of
application in section office. |
|
|
|
|
| b) |
Collection of Security Deposit and execution of
agreement. |
- |
Within 7 days from the date of sanction if
applicant is ready. |
|
|
|
|
| c) |
Execution of HT line extension, Double Pole
structure works subject to availability of materials, priority and site condition. |
- |
Within 30 days after payment of Security Deposit. |
|
|
|
|
| d) |
Provision of metering arrangements |
- |
10 days after completion of work. |
|
|
|
|
| e) |
Effecting service connection after payment, after
fixing the meter at the consumer premises. |
- |
Within 10 days after completion report with all
the required clearances by the applicant. |
|
|
|
|
| B) |
Schemes costing more than Rs.2,00,000
but less than Rs.5,00,000: |
|
|
| a) |
Preparation of estimate for extension of power
supply. |
- |
Within 30 days from the receipt of application in
section office. |
|
|
|
|
| b) |
Collection of Security Deposit and execution of
agreement. |
- |
Within 7 days from the date of sanction if
applicant is ready. |
|
|
|
|
| c) |
Execution of HT line extension, Double Pole
structure works subject to availability of materials, priority and site condition. |
- |
Within 60 days after payment of Security Deposit. |
|
|
|
|
| d) |
Provision of metering arrangements |
- |
10 days after completion of work. |
|
|
|
|
| e) |
Effecting service connection after payment, after
fixing the meter at the consumer premises. |
- |
Within 10 days after completion report with all
the required clearances by the applicant. |
|
|
|
|
| C) |
Schemes costing more than
Rs.5,00,000: |
|
|
| a) |
Preparation of estimate for extension of power
supply. |
- |
Within 30 days from the date of receipt of
application in section office. |
|
|
|
|
| b) |
Collection of Security Deposit and execution of
agreement. |
- |
Within 7 days from the date of sanction if
applicant is ready. |
| c) |
|
|
|
| i) |
Execution of HT line extension, Double Pole structure works
subject to availability of materials, priority and site condition (without erection of new
feeder). |
- |
Within 90 days after payment of Security Deposit. |
|
|
|
|
| ii) |
Extension of line work involving provision of new /
additional feeder arrangement from the sub-station. |
- |
Within 180 days after payment of security deposit |
|
|
|
|
| d) |
Provision of metering arrangements |
- |
10 days after completion of work. |
|
|
|
|
| e) |
Effecting service connection after payment, after fixing the
meter at the consumer premises |
- |
Within 10 days after completion report with all the required
clearances by the applicant. |
|
NOTE: In the case of outlying regions,
if sanctions are required from Puducherry another 15 days time may be added to the
time indicated under each category.
II. ISSUE OF POWER FEASIBILITY CERTIFICATE
(A) |
LOW TENSION SERVICE CONNECTION: |
|
|
| (i) |
If the total load in addition to the proposed
load is within 90% of the capacity of existing transformer and the scheme;
proves to be self-remunerative. |
- |
Power Feasibility Certificate
will be issued within 10 days after receipt of the application. |
| (ii) |
If the total load in addition to the proposed
load is more than 90% of the capacity of existing transformer. |
- |
Will be issued within 30 days after receiving the
application. |
(B) |
HIGH TENSION SERVICE CONNECTION: |
|
|
| (i) |
If the contracted maximum demand is less than 500
KVA. |
- |
Within 30 days after submitting all the necessary
documents. |
| (ii) |
If the contracted maximum demand is including or
more than 500 KVA. |
- |
After submitting all the necessary documents
within20 days after obtaining the Government sanction. |
III OTHER WORKS
| (i) |
Rectification of Fuse-off Call Complaints at the
Consumer end. |
- |
Immediately |
| (ii) |
Rectification of High tension Power interruption. |
- |
Immediately, if
possible defect will be attended on the same day. If the defect prevails, the same will be
rectified on the next day. |
| (iii) |
Fault rectification in distribution transformer. |
- |
Will be rectified
within three days. If the capacity of other nearest transformer is adequate, supply will
be extended through alternate line on the same day, if feasible. |
SUPERINTENDING
ENGINEER - I
APPLICATION FOR NEW DOMESTIC SERVICE CONNECTION-LOW
TENSION
CHECK LIST OF DOCUMENTS
| SL No |
Details |
Enclosed |
Not Applicable |
Remarks |
| 1 |
Application Form duly filled up |
Yes |
No |
|
|
| 2 |
Attested copy of the registered ownership
document or registered lease agreement with No Objection Certificate of the property
Owner. |
Yes |
No |
|
|
| 3 |
Power Feasibility Certificate for multistoreyed
buildings with connected load exceeding 25 kW. |
Yes |
No |
|
|
| 4 |
Puducherry Planning Authority approval for
multistoreyed buildings as required under clause 16 of the departmental terms and
conditions of supply of electricity. |
Yes |
No |
|
|
| 5 |
For cases with Door No., Street Name not
identified in ownership Document, Affidavit declaring that the premises for which the
connection is sought is same as in the ownership document. |
Yes |
No |
|
|
| 6 |
Certificate from the electrical contractor
confirming use of ISI certified materials and equipments only, in the building
electrification. |
Yes |
No |
|
|
| 7 |
Copy of the Occupancy certificate for servicing
of multistoreyed building installations. |
Yes |
No |
|
|
| 8 |
2 Self addressed stamped envelopes. |
Yes |
No |
|
|
Note:
For enhancement of load under the existing policies, all the
above particulars along with copy of the latest Current Consumption Bill and Payment
Receipt should be submitted.
APPLICATION FOR NEW COMMERCIAL SERVICE CONNECTIONS-LIGHTING
AND AIR-CONDITION LOAD
CHECK LIST OF DOCUMENTS
| SL No |
Details |
Enclosed |
Not Applicable |
Remarks |
| 1 |
Application Form duly filled up. |
Yes |
No |
|
|
| 2 |
Attested copy of the registered ownership
document or registered lease agreement, with No Objection Certificate of the property
Owner. |
Yes |
No |
|
|
| 3 |
Power Feasibility Certificate for load exceeding
10 kW |
Yes |
No |
|
|
| 4 |
Puducherry Planning Authority Approval for
multistoreyed buildings as required under clause 16 of the Departmental Terms and
Conditions of Supply of Electricity (or) No Object Certificate / Sanction Plan issued by
Competent Authority (PPA). |
Yes |
No |
|
|
| 5 |
For cases with Door No., Street Name not
identified in ownership document, affidavit declaring that the premises for which the
connection is sought is same as in the ownership document. |
Yes |
No |
|
|
| 6 |
Certificate from the electrical contractor
confirming use of ISI certified materials and equipments only, in the building
electrification. |
Yes |
No |
|
|
| 7 |
Copy of the Occupancy Certificate for servicing
of multistoreyed building installations . |
Yes |
No |
|
|
| 8 |
Two Self Addressed Stamped envelopes |
Yes |
No |
|
|
Note:
(A) For enhancement of load under the existing polices, all
the above particulars along with copy of the latest Current Consumption Bill and Payment
Receipt should be submitted.
(B) Separate Application to be filed for Lighting load and
Air-Condition load.
APPLICATION FOR NEW LT INDUSTRIAL SERVICE CONNECTION
CHECK LIST OF DOCUMENTS
| SL No |
Details |
Enclosed |
Not Applicable |
Remarks |
| 1 |
Application Form with signature and seal. |
Yes |
No |
|
|
| 2 |
Attested copy of Registered Ownership Document. |
Yes |
No |
|
|
| 3 |
Attested Copy of valid Power feasibility
certificate. |
Yes |
No |
|
|
| 4 |
Attested copy of approval from Puducherry
Planning Authority with a Copy of Approved plan. In case of existing building, NOC
should be enclosed. |
Yes |
No |
|
|
| 5 |
Attested copy of SSI Provisional Certificate. |
Yes |
No |
|
|
| 6 |
In case of partnership firm Registered
Partnership Deed should be enclosed (or) Certificate of registration issued by the
Registrar of Companies. |
Yes |
No |
|
|
| 7 |
In case of Company, Memorandum and Article of
Association and Certificate of Incorporation should be enclosed. |
Yes |
No |
|
|
| 8 |
In case of Partnership / Company, letter for
Authorised Signatory to deal with matters related to Electricity Department. |
Yes |
No |
|
|
| 9 |
Attested Copy of Valid Commune Panchayat Licence
/ Permission with permitted load mentioned. |
Yes |
No |
|
|
| 10 |
Attested Copy of Valid NOC / consent order,
Puducherry Pollution Control Committee for Air and Water. |
Yes |
No |
|
|
| 11 |
Attested copy of Valid approval / licence from
inspector of factories Department with copy of approved plan |
Yes |
No |
|
|
| 12 |
Attested copy of state ground water unit
clearance for ground water utilization if the industry is water based |
Yes |
No |
|
|
| 13 |
Details of machineries with capacity to be
installed. |
Yes |
No |
|
|
| 14 |
Peak Hour load restriction undertaking |
Yes |
No |
|
|
| 15 |
Certificate from the Electrical contractor
confirming use of ISI certified materials and equipments only, in the building
electrification work. |
Yes |
No |
|
|
| 16 |
Two Self Addressed Stamped envelopes |
Yes |
No |
|
|
Note:
For enhancement of load under the existing policies, all the
above particulars along with copy of the latest Current Consumption Bill and Payment
Receipt should be submitted
APPLICATION FOR HT INDUSTRIES
CHECK LIST OF DOCUMENTS
| SL No |
Details |
Enclosed |
Not Applicable |
Remarks |
| 1 |
Application Form with signature and seal (7
copies). |
Yes |
No |
|
|
| 2 |
Sale Deed/Registered Lease Deed / PIPDIC
allotment order (2 copies) |
Yes |
No |
|
|
| 3 |
Power feasibility certificate (3 copies) |
Yes |
No |
|
|
| 4 |
Puducherry Planning Authoritys approval(3
copies) |
Yes |
No |
|
|
| 5 |
Provisional registration certificate from
Industries Department, Puducherry ( 3 copies) |
Yes |
No |
|
|
| 6 |
Registered partnership deed (3 copies) |
Yes |
No |
|
|
| 7 |
In case of Company, Memorandum of Article of
Association and certificate of incorporation (2 copies) |
Yes |
No |
|
|
| 8 |
Power of attorney to sign the HT application (3
copies) |
Yes |
No |
|
|
| 9 |
Commune Panchayat Licence / permission (3 copies) |
Yes |
No |
|
|
| 10 |
Clearance from Department of Science and
Technology and Environment (3 copies) |
Yes |
No |
|
|
| 11 |
Clearance from inspector of factories and Boilers
(3 copies) |
Yes |
No |
|
|
| 12 |
Clearance from State Ground water unit /
Agricultural Department if the industry is water based (3 copies) |
Yes |
No |
|
|
| 13 |
Details of Machineries with capacity to be
installed |
Yes |
No |
|
|
| 14 |
Peak Hour Demand Restriction undertaking letter |
Yes |
No |
|
|
| 15 |
Concurrence letter from the applicant in case of
HT to near the cost of 50% of the cost towards erection and extension of lines over and
above 1 lakh (3 copies) |
Yes |
No |
|
|
| 16 |
Site layout (3 copies) |
Yes |
No |
|
|
| 17 |
No due certificate in case of enhancement |
Yes |
No |
|
|
| 18 |
Two Self Addressed Stamped envelopes |
Yes |
No |
|
|
APPLICATION FOR NEW LT IRRIGATION PUMP SET (AGRICULTURAL SERVICE
CONNECTION)
CHECK LIST OF DOCUMENTS
| SL No |
Details |
Enclosed |
Not Applicable |
Remarks |
| 1 |
Application Form 2 duly filled up. |
Yes |
No |
|
|
| 2 |
Attested copy of the registered ownership
document or registered lease agreement, with No Objection Certificate of the property
owner. |
Yes |
No |
|
|
| 3 |
In case the water is drawn from river/
channel/sub-channel Nallah, etc, by installing pumpset the copy of the NOC from the
concerned irrigation department, Public Work Department or Revenue Department or any other
department to lift water shall be submitted. |
Yes |
No |
|
|
| 4 |
In case under ground water is tapped copy of the
attested clearance certificate issued from the State ground water unit. |
Yes |
No |
|
|
| 5 |
Certificate of ownership authenticated by the
authorised Revenue official of that area and in case there are more than one person who
are owners of the well, the consent letter from other owners. |
Yes |
No |
|
|
| 6 |
Certificate from the electrical contractor
confirming use of ISI certified materials and equipments only and compliance on energy
conservation measures, in installing agricultural pumpsets. |
Yes |
No |
|
|
| 7 |
Two Self Addressed Stamped envelopes. |
Yes |
No |
|
|
Note:
For enhancement of load under the existing policies, all the above
particulars along with copy of the latest Current Consumption Bill and Payment Receipt
should be submitted.
|