IMPORTANT ON-GOING/PROPOSED CAPITAL WORKS
I. Transmission Scheme works
Establishment of new 230 KV
Auto Sub-station at Thondamanatham village in Puducherry at an estimated cost of Rs. 55.00
Crores. The work has been entrusted to Power Grid Corporation of India Limited.
Establishment of new 33/11 KV
Sub-station at Yanam and augmentation of existing 132 KV Yanam Sub-Station at a cost of
Rs. 8.78 Crores. The work is being carried out by the Power Grid Corporation of India and
is under progress.
Renovation and modernization
of existing Marapalam, Kurumbapet and Villianur 110 KV Sub-Stations at a total estimated
cost of Rs. 11.60 Crores.
Strengthening of existing
Villianur-Bahour 110 KV line at an estimated cost of Rs. 6.00 Crores.
Interlinking of existing 110
KV Sub-Stations with provision of back-up protection relays at an estimated cost of Rs.
30.00 lakhs.
11th Five Year Plan
(2007-2012) Schemes:
Establishment of 230 KV
Sub-station at Polagam in Karaikal.
Formation of 230 KV grid
synchronising proposed 230 KV Sub-station in Karaikal region with 230 KV Sub-stations at
Puducherry region.
Establishment of five new 110
KV Sub-stations in Puducherry region, at Venkatanagar, Thirubhuvanaipalayam, Karasur,
Thavalakuppam & Lawspet, with capacity addition of 288 MVA and associated transmission
lines.
II. Cable Conversion Scheme Works
During the year 2006-07, it
has been proposed to lay 5.7 Kms. of HT and 33.0 Kms. of LT under ground cables in
Puducherry and Karaikal regions.
Thereafter, 1,800 numbers of
existing overhead service connections will be converted into under ground system.
Simultaneously 150 numbers of street lights will also be converted into under ground cable
system.
In order to strengthen the
existing power distribtuion system in the Puducherry town area, 5 numbers of new 630 KVA
transformers will be erected and the capacity of existing 5 numbers of 315 KVA
transformers will be enhanced to 630 KVA.
11th Five Year Plan
(2007-2012) Schemes:
Modernization of existing 11
KV Ring Main System in Puducherry town area.
|